Internal Project Planner
A dynamic tool for estimating pilot project costs and outlining key research tasks. Use this to plan the next phase of development.
| Line Item | Cost per Unit (USD) | Total Cost (10 Units) | Notes/Assumptions | ||
|---|---|---|---|---|---|
| A. Land & Site Preparation | |||||
| Land Acquisition (1-2 acres) | - | $7,500 | Based on rural Kenyan land prices of ~$3,800/acre. | Estimated higher cost due to demand. | Estimated lower cost for rural land. |
| Site Clearing & Excavation | $1,000 | $10,000 | Based on Kenyan rates. | ||
| Foundation (Concrete Slabs) | $3,000 | $30,000 | Includes materials and labor. | ||
| Utility Trenching & Prep | $750 | $7,500 | For water, sewage (septic), and electrical. | ||
| B. Modular Units & Logistics | |||||
| Unit Cost (FOB China) | $6,890 | $68,900 | Based on 40ft Expandable Home option. | ||
| Shipping, Tariffs & Fees | $6,000 | $60,000 | Based on ~46.5% import duties/levies for Kenya. | Est. ~35-45% cumulative duties. | Est. ~20-30% VAT + customs duties. |
| Last-Mile & Installation | $4,000 | $40,000 | Heavy-haul trucking, crane rental, labor. | ||
| C. 'Smart Town' Technology | |||||
| Surveillance System | $400 | $4,000 | Assumes 2-3 NVRs + 4K cameras. | ||
| Community Wi-Fi Network | $300 | $3,000 | Central outdoor mesh + in-home extenders. | ||
| Smart Meters (Water & Electric) | $550 | $5,500 | Upfront hardware cost. | ||
| Solar Microgrid (Centralized) | - | $60,000 | Sized for 10 homes + tech. | ||
| D. Soft Costs | |||||
| Permits, Legal & Professional Fees | - | $15,000 | Includes EIA, NCA, county permits, local partners. | Similar permit complexity expected. | May be lower due to different regulations. |
| E. Contingency Fund (20%) | |||||
| Contingency (20% of Subtotal) | - | $50,280 | 20% of all items A-D. | ||
| TOTAL ESTIMATED BUDGET | $301,680 | Provides a target seed funding range. | |||
Supplier & Logistics Research List
Actionable to-do list for gathering specific data needed to refine the project budget and plan.
B. Modular Units
- **Task:** Identify 5-10 top-rated manufacturers on Alibaba, Made-in-China, etc.
- **Task:** Get formal quotes for the "$1,900" and "$6,890" unit types.
- **Data:** Price per unit (at 10, 50, 100 units).
- **Data:** Customization options and costs.
- **Data:** Production lead time.
- **Data:** Flat-pack shipping specs (how many units per 40ft container?).
B. Logistics & Tariffs
- **Task:** Research 3-5 freight forwarders (e.g., Basenton).
- **Data:** Cost for 40ft container: China -> Mombasa (Kenya).
- **Data:** Cost for 40ft container: China -> Lagos (Nigeria).
- **Data:** Cost for 40ft container: China -> Durrës (Albania).
- **Task:** Research import duties for "prefabricated buildings" in all 3 target countries.
- **Task:** Identify local heavy-haul trucking companies near target ports.
- **Data:** Get quote for 100km inland heavy-haul.
C. 4K Surveillance System
- **Task:** Research bulk suppliers for 4K PoE cameras and NVRs.
- **Suppliers:** Avigilon, Axis, Dahua, Hikvision.
- **Data:** Price per 8-camera 4K NVR kit.
- **Data:** Price for 1000m spool of outdoor CAT6 cable.
- **Data:** Shipping costs and import duties for electronics in target regions.
C. Community Wi-Fi
- **Task:** Research commercial outdoor mesh systems.
- **Suppliers:** Calix, Eero, TP-Link (Deco), Netgear (Orbi).
- **Data:** Price for 1x outdoor "hub" unit.
- **Data:** Price for 10x 2-pack in-home "spoke" units.
- **Data:** ISP/Satellite internet setup and monthly costs in rural Kenya/Nigeria/Albania.
C. Smart Utilities
- **Task:** Research off-grid solar microgrid providers.
- **Suppliers:** Tesla (Powerwall), or alternatives.
- **Data:** Get quote for a system to power 10 homes (est. 30-50kW solar + 100kWh battery).
- **Task:** Research smart water & electric meters.
- **Suppliers:** Bluebot, Neptune, etc.
- **Data:** Price per smart water meter (x10).
- **Data:** Price per smart electric meter (x10).
D. Legal & Permits
- **Task:** Identify 3 local architectural/engineering firms in each target region.
- **Task:** Research official government sites for:
- Building Permit ("Alvará") process (Brazil).
- NCA registration process (Kenya).
- Building Permit (PD 1096) process (Philippines - for future).
- **Data:** Estimated cost for an Environmental Impact Assessment (EIA) in Kenya.